Standalone pump (Component B), grid pump solarise (Component C), ya hybrid with backup — 2026 mein ye sabse zyada pucha jane wala sawal hai. Light cut, inverter trip, aur Rajasthan curtailment ke baad aur confusion badh gaya.
Ek "best" pump sab ke liye nahi — grid quality, sinchai ka time, subsidy, aur shaam ko paani zaroori hai ya nahi — ye decide karte hain.
Short rule: Sirf din mein paani + line nahi → Component B. Purana grid pump + stable feeder → Component C. Roz light jati hai / shaam ko paani → hybrid socho.
Comparison table — B vs C vs Hybrid
| Factor | Component B | Component C | Hybrid |
|---|---|---|---|
| PM-KUSUM | B — naya standalone | C — grid pump solar | B + battery / dual inverter (state confirm) |
| Grid | Pump ke liye zaroori nahi | Purani ag connection | Grid + solar; battery optional |
| Light cut par? | Haan (dhoop mein) | Aksar nahi | Haan (battery / mode par depend) |
| Subsidy | 60% tak (30+30) | ~30% CFA + state | Battery par subsidy limited |
| 5 HP cost | ₹3–4L → ₹1.2–1.6L | Purana pump ho to kam add-on | +₹50k–1.5L battery par |
| Export | Nahi | State rule se export | Design par depend |
| Best for | Door ka bore, diesel | Stable grid, electric pump | Weak grid + shaam sinchai |
| Risk | HP zyada, raat paani nahi | Trip, curtailment | Mehnga, battery 5–7 saal |
Component B — standalone
Solar → controller → pump. DISCOM ko export nahi. Dhoop strong ho to chalta hai.
Fayda: Simple; light cut mein bhi; 60% subsidy slab.
Nuksan: Raat ko paani nahi (tank nahi to); grid pump pehle se ho to duplicate; array garmi ke worst din ke hisaab se.
B tab lo jab: Naya bore, diesel mehnga, sinchai subah–dopahar hi.
Cost: 3/5/7.5 HP kharcha.
Component C — grid pump solar
Purane bijli wale pump par solar. Din solar priority; badal par grid; extra unit export ho sakti hai.
Fayda: Purana pump use; cloudy par thodi grid help.
Nuksan: Light cut par band; voltage trip; export fight; B se kam CFA.
C tab lo jab: Grid theek, pump naya, DISCOM se adjust OK.
Problems: Component C guide.
Hybrid — kab extra paisa dena smart hai
Farmer language mein hybrid = solar + battery shaam ke liye, ya dual inverter jo light cut par limited solar se chalaye.
Fayda: Shaam 4–6 baje feeder down ho tab bhi paani; weak voltage par smooth start.
Nuksan: ₹50k–1.5L+ extra; battery 5–7 saal baad change; subsidy poori battery cover nahi karti; mechanic kam milega.
Hybrid tab lo jab: Sabzi / nursery ko shaam paani, roz trip, flowering par light cut.
Detail: power cut par kya hota hai.
Decision — simple flow
Pehle se grid pump hai?
├── Nahi → Component B
└── Haan → Grid season mein stable 6+ ghante?
├── Nahi → B naya pump YA hybrid
└── Haan → Shaam 6 ke baad paani?
├── Haan → Hybrid ya B + tanki
└── Nahi → Component C
5 HP — cost vs saving (andaza)
| Option | Subsidy ke baad | 5 saal note |
|---|---|---|
| B | ₹1.2–1.6L | Grid unit zero pump ke liye |
| C add-on | ₹80k–1.5L | Bill kam; export state par |
| Hybrid | ₹2–3L total | Battery change ka kharcha yaad rakho |
Bill savings cases se apna hisaab lagao.
Choose karte waqt 5 galtiyan
- Dead feeder par C — hamesha trip; B hona chahiye tha
- Chhoti battery hybrid — 30 minute — disappointment
- B bina tank — raat ko pashu ka paani nahi
- Non-ALMM panel — subsidy reject (ALMM guide)
- Dealer C push kare margin ke liye — 3 quote lo
2026 policy note
PM-KUSUM 2.0 aur Agri-PV alag topic — 2.0 update. Pump choice alag hai Component A MW plant se.
Confusion ho to pehle paani ki tanki — sasta hybrid trick. Din bhar bharo (B ya C), raat gravity se sincho.
Disclaimer: State wise rule alag. pmkusum.mnre.gov.in verify karo. Ask Kisan pump bechta nahi.
Last verified: June 2026.
अक्सर पूछे जाने वाले प्रश्न
Component B aur Component C mein kya farak hai?
Component B standalone solar pump hai — grid ki zaroorat nahi, 60% subsidy tak. Component C purane grid pump par solar lagata hai — din mein solar, kam par bijli, extra unit export ho sakti hai. Hybrid mein battery ya dual mode se light cut par bhi backup milta hai.
Power cut par on-grid solar pump chalega?
Aksar nahi — safety ke liye grid-tie inverter band ho jata hai. Component C bhi light jane par ruk sakta hai jab tak hybrid design na ho. Component B dhoop mein bina grid ke chal sakta hai.
Hybrid pump mehnga hai, worth it hai?
Hybrid mein battery ya special inverter extra kharcha — ₹50,000 se ₹1.5 lakh tak. Tab lena jab shaam ko bhi paani chahiye ya feeder roz trip kare. Sirf din mein 6–8 ghante sinchai ho to B ya C kaafi ho sakta hai.
Subsidy kis par milegi?
Component B aur C dono par central/state support hai — pmkusum.mnre.gov.in par active component check karo. Battery wala hybrid har state mein full benchmark par nahi aata — quote se pehle nodal se puchho.
Rajasthan mein kya choose karte hain?
Weak feeder par kai log Component B prefer karte hain. Jahan grid stable hai wahan Component C. State portal steps ke liye Rajasthan guide dekho.