Bhai, Rajasthan solar ka hub hai — par 2026 mein ek dikkat bhi khuli: curtailment, matlab plant ko dhoop mein bhi bijli kam/band bhejne ko kehna. Mercom India, Economic Times, The Hindu business pages jaisi reporting mein January 2026 se ~11.5 GW capacity par curtailment ka zikr aur 4 GW+ peak shutdown aaya hai.
Agar tum zameen lease kar rahe ho, open-access soch rahe ho, ya PM-KUSUM Component A — ye sirf news nahi, tumhari kamai hai.
Data disclaimer: GW figures industry media se hain (Mercom, ET, Hindu BL style, 2026). Government ka alag number ho sakta hai. Ye article risk samajhne ke liye hai, kisi agency par case ke liye nahi.
Curtailment seedha matlab
Curtailment = suraj full hai par plant ko grid par kam/band export karna padta hai.
Rajasthan 2026 mein reasons:
- Transmission kam — RE zyada, line kam peak par
- T-GNA / scheduling — market rules
- Din ke beech demand — solar zyada, load kam
- Interstate corridor — bahar buyer tak power nahi ja paati
Kisan ko symptom: rent late, generation-linked lease kam, open-access credit kam
~11.5 GW headline — kaise padhein?
Mercom wagaira (May–June 2026):
- ~11.5 GW capacity exposed / affected (wording source par badalti hai)
- Kuch din 4 GW+ ek saath back down
| Baat | Matlab |
|---|---|
| 11.5 GW | Hamesha “sab band” nahi — cumulative / exposed capacity type reporting |
| Peak 4 GW+ | Dhoop ke peak hours par revenue loss |
| Jan 2026 se | Naya build + purani lines = tension |
Investment se pehle latest article cross-check karo.
~23 GW RE vs ~18.9 GW line — press wali kahani
ET / Mercom style analysis:
- Installed RE ~23 GW (Rajasthan)
- Evacuate karne ki capacity ~18.9 GW ke aas-paas cite
- ~4 GW gap = dhoop par bandi
Simple: naliya badi, outlet chhota — paani (power) ruk jata hai.
Transmission nayi banegi — par saal lagte hain; lease aaj sign ho sakta hai.
T-GNA — farmer language mein
T-GNA = generator ko shared grid par power bhejne ka access / schedule framework.
Tumhare liye:
- Corridor full → solar pehle kam ho sakta hai (merit order fight chal rahi hai)
- Brochure “must-run RE” hamesha ground par nahi — dispute hoti hain
Broker bole “dhoop = pakka paisa” — pucho: PPA mein likha hai ya WhatsApp par?
Kaun affect — tum kis bucket mein ho?
Zameen lease (utility solar)
- Fixed rent/acre = thoda safe
- Generation linked = curtailment year mein risk
- 25 saal lease bina curtailment clause = danger
Open-access investor
- Units kam → paisa kam
- ALMM (June 2026) + curtailment = double pressure — ALMM guide
Sirf Component B pump
- Off-grid → grid curtailment nahi
- Sinchai ke liye abhi reliable option — bill savings
Component A / Agri-PV
- 5 km substation zaroori par kaafi nahi — feeder bhi congest ho sakta hai
- PM-KUSUM guide, 2.0 agrivoltaics
Lease sign se pehle — 5 sawal
- Rent fixed ya generation par?
- Curtailment risk kiska?
- Payment security — prepay, escrow?
- Evacuation / connectivity approved likhit?
- Exit agar plant months band rahe?
Sinchai priority ho to 60% subsidy wala pump (₹1.2–1.6 lakh share illustrative) uncertain lease se compare karo — 3HP–7HP cost.
Bottom line
- ~11.5 GW aur 4 GW+ peak — 2026 press mein serious signal
- Problem: zyada solar, kam transmission
- Off-grid pump safe; lease / open access risky
- Contract padho — brochure PLF par blind mat karo
Disclaimer: Stats Mercom, ET, Hindu type industry reporting se — indicative. Legal/investment advice nahi. Lease se pehle vakil + developer documents verify karo.
Last verified: June 2026.
अक्सर पूछे जाने वाले प्रश्न
Rajasthan mein 2026 mein kitna solar curtail hua?
Industry reporting (jaise Mercom India, May–June 2026) ke hisaab se January 2026 se lagbhag 11.5 GW RE capacity par curtailment ka asar bataya gaya, kuch din peak shutdown 4 GW se upar. Figure source par badal sakti hai — government ledger mat samajhna.
T-GNA kya hai?
T-GNA transmission aur grid access rules se juda hai — jab line bhari hoti hai to strong sun par bhi solar plant ko kam ya band export karne ko kaha ja sakta hai. Lease ya open-access income isse hit ho sakti hai.
Kya PM-KUSUM solar pump par curtailment lagta hai?
Component B off-grid pump par grid curtailment nahi lagta. Jo zameen lease karke bada plant ya open-access mein paisa lagate hain, un par developer payment / generation kam ho sakti hai.
Transmission gap kya hai?
Press mein aksar ~23 GW installed RE vs ~18.9 GW evacuation capacity wali baat aati hai — peak dhoop par power nikal nahi paati, isliye curtailment.
Kya ab zameen lease par solar dena chahiye?
Sirf ₹/acre rate sun kar 25 saal lease mat sign karo. PPA mein curtailment compensation, evacuation approval, risk kiska — likhit pucho. Irrigation ke liye pump subsidy path bhi compare karo.